Mumbida Wind Farm

Case study

Mumbida Wind Farm

We have provided full asset management services for this 55MW wind farm in Western Australia for Foresight Group since 2023, integrating the site into our 24/7 Remote Operations Centre and reducing operational costs through an updated Asset Management Plan.

Turbines at Mumbida Wind Farm, Western Australia
Industries
Renewable & New Energy
Services
Operations, Maintenance & Readiness; Asset Management & Advisory; Control Centre & Specialised Services

Overview

SPIE Power Services provides full asset management services for the 55MW Mumbida Wind Farm in Mount Hill, Western Australia, for owner Foresight Group. Comprising 22 GE 2.5XL wind turbine generators, the site has been under our management since 2023, when we took over from the original equipment manufacturer.

The challenge

Foresight required a dedicated, independent O&M partner to replace the outgoing OEM and take full ownership of asset management for the wind farm. The transition needed to be seamless, maintaining turbine availability and reliability while improving operational cost efficiency and introducing a site-specific safety and environmental framework.

Our approach

We assumed full operational responsibility for the site, developing a bespoke HSEQ and Environmental Management Plan tailored to Mumbida's specific conditions. We also reviewed and updated the existing Asset Management Plan to reduce operational costs and optimise long-term maintenance strategies.

The solution

We integrated Mumbida into our 24/7 Remote Operations Centre, enabling continuous monitoring and rapid fault response. By deploying our specialised wind technician team and applying our in-house asset management capabilities, we drove meaningful improvements in reliability and operational performance across the 22-turbine fleet.

Key outcomes

What the project delivered

  • Successfully transitioned full asset management from OEM to SPIE Power Services with operational continuity maintained.

  • Introduced a site-specific HSEQ and Environmental Management Plan to raise safety and compliance standards.

  • Reduced operational costs through an updated Asset Management Plan focused on long-term performance optimisation.

  • Achieved 24/7 remote monitoring coverage through integration with our central Remote Operations Centre.